Chelsea’s Eastern Avenue Battery Plant Lines Up $850 Million. It Would Be the Largest on the East Coast

Lea este artículo en español

The company building a giant battery storage plant at 284 Eastern Avenue in Chelsea says it has lined up about $850 million to pay for it, and that the project, called Energizar, will be the largest battery storage system on the East Coast when it starts running at the end of 2027.

Flatiron Energy announced on October 15 that it had closed the financing for the 1,200-megawatt-hour project, according to pv magazine USA and other energy trade publications. The money is a package of construction and bridge loans, term loans, letters of credit, a preferred equity investment and an agreement by two Fortune 500 companies to buy part of the project’s federal tax credits. Nord/LB, Santander and Societe Generale led the lending, joined by Investec, East West Bank and Siemens Financial Services.

Advertisements

Flatiron says the batteries will store electricity and send it back to the grid when demand peaks, cutting the Boston area’s reliance on fossil fuel power plants at those times. The company is aiming for commercial operation in the fourth quarter of 2027.

Bigger, and later, than in July

The numbers have changed since the summer. In July, Eversource, National Grid and Unitil filed long-term contracts with three battery projects, and those filings listed Energizar at 250 megawatts and 1,000 megawatt-hours, with operation starting in the second quarter of 2027, according to Utility Dive. The October announcement puts the project at 1,200 megawatt-hours, gives no megawatt figure and pushes the start back two quarters. It does not explain the changes or say whether the utility contracts changed, as the trade site mgrid.org pointed out.

The same round of contracts included a far larger battery nearby: Jupiter Power’s Trimount project in Everett, at 700 megawatts and 2,800 megawatt-hours.

What Chelsea approved

The project came to Chelsea’s boards as Energizar Storage LLC in 2024. The original plan put the batteries inside a building. In February, the Planning Board took up a change that eliminated the building and instead placed the battery units in separate outdoor enclosures behind a wall. The Zoning Board of Appeals and the Conservation Commission had already found the change minor.

Hunter Prange of Flatiron told the Planning Board on February 24 that the wall would be 20 feet high, that a living green wall had been ruled out because it could catch fire, and that the company was considering murals and landscaping to break it up. He said the gate would open only with a badge, the Fire Department would get a key, and the company was talking with a camera supplier about giving police access. One or two people would be on site for maintenance, he said, but not around the clock.

Board member Sarah Ritch raised concerns about the side facing the commuter rail tracks, where Prange said there would be a 10-foot chain link fence, and about the site having no roof. Prange said the batteries sit in metal containers, so stray embers should not be a problem, and that the company would train regularly with the Fire Department. Asked what happens when the batteries reach the end of their life, he said the land is not contaminated, the batteries would not contaminate it and the only liquid on site would be transformer oil, with pits built to catch any leak. He said a substation next door makes the site attractive for energy companies.

Member Eric Czernizer said he supported the project but called it “an extremely different change” and argued it should count as a major one. He changed his vote, and the board approved the change as minor, 5-0, with a lattice design for the wall and an opaque wall along the railroad side. No one from the public spoke.

Several city councillors have raised concerns about the site, according to the minutes of the council’s Public Safety subcommittee in April. Fire Chief John Quatieri told the subcommittee the battery site is in the response area of the Mill Hill fire station, not Central Station.

Graphic: chelseamass.net.

Update, November 12

Flatiron Energy broke ground on Energizar on Thursday, November 12, the company said in a news release. Lieutenant Governor Kim Driscoll attended the ceremony with state and local officials, community partners and labor representatives.

The release settles the size question raised above: it describes the plant as 250 megawatts and 1,200 megawatt-hours, and says it is expected to be the largest battery storage facility in the Northeast when finished. Consigli Construction Co. is leading construction. Flatiron still expects commercial operation in the fourth quarter of 2027.

On what Chelsea gets, the release says Flatiron will make “significant investments” over the life of the project in the city’s Green New Economy Program, which the city will direct toward workforce development, community development, youth development and community empowerment. It gives no dollar amount. The company also says it is working to connect Chelsea residents with construction jobs, pointing to a Chelsea Trade Union Summit held earlier this year with the city, La Colaborativa and Greater Boston trade unions, and that it is providing ongoing emergency response training to the Chelsea Fire Department.

“Energizar represents a significant investment in our city, bringing new economic opportunities and resources to our community while supporting the region’s long-term energy needs,” City Manager Fidel Maltez said in the release.

Gladys Vega, chief executive of La Colaborativa, said in the release that she is “encouraged by the commitment to connecting local residents with workforce development, training and career opportunities.” Roseann Bongiovanni, executive director of GreenRoots, said the project is a chance to advance cleaner energy “while prioritizing meaningful community engagement and long-term benefits for local residents.”

The release does not say how many construction or permanent jobs the project will create or how many will go to Chelsea residents.