Standard Box Fire

8 Alarm Blaze Destroys
Standard Box Company

On June 6, 1997 at 6:10 A.M. Kenneth Rice, a worker at the Standard
Box Company at 28 Gerrish Avenue, spotted flames shooting from the
wax machine, a machine designed to heat up automatically. Rice
immediately called 911. When firefighters arrived, Rice accompanied
them into the building to show them the location of the fire, which
then was only a small blaze.In a matter of minutes the fire changed
course and intensified and Rice had to climb out of the building down
a ladder. Two firefighters, Lieutenant Michael Connors and Albert
Peters brought hoses to the fourth floor in an attempt to extinguish
the blaze, but when the smoke caused complete blackout conditions
inside the building, they attempted to follow their hose lines back
to safety. The hoses were wrapped around machinery, confusing their
efforts to follow the lines back to safety and their air supply tanks
on their backs were rapidly dwindling. When the two firefighters saw
a conveyor shaft that dropped approximately fifteen feet to the floor
below where there was fresh air and no sign of fire, they decided to
jump to safety. Although the plunge down the shaft saved their lives,
both men were injured and had to be transported to the Massachusett
General Hospital in Boston. Connors was suffering from a compression
fracture to his vertebrae and Peters suffered multiple traumas as a
result of the fall. He was treated and released.

Firefighters continued to bring hoses into the building to fight the
fire. For awhile it seemed they were making progress in extinguishing
the blaze, but it was soon reported that oils in the building were
feeding the fire. At 8:34 A.M. a fifth alarm was called and
firefighters vacated the building and switched their attack on the
fire to the outside of the building. One of the major problems they
experienced fighting the fire from the outside of the building
stemmed from the fact that the roof of the building was difficult to
ventilate and a lot

Deputy Chief Joseph VonHandorf and Chief Louis
Addonizio direct efforts as the wall of the Standard Box Company
explodes behind them.

of the windows were boarded up which allowed heat in the building to
intensify. The fire continued to worsen and the building was in
danger of collapse. At this point, all equipment was moved away from
the building, forcing firefighters to shut down lines in order to
relocate the equipment. About 60 minutes later, the roof and walls
gave way, crashing into nearby Boston Edison lines. Firefighters
continued to battle the blaze, keeping watch for flying embers which
landed as far away as Bellingham Square. At 9:38 A.M. a seventh alarm
was sounded and firefighters began to call for more help to get
additional water on the fire. The eighth alarm was sounded at 9:41
A.M. and reserve forces were called in to make sure the fire embers
did not ignite surrounding buildings.

Firefighters pour water on the fire

Standard Box Company consumed by the flames

The fire was not completely extinguished until 3:45 P.M. on Sunday,
two days later. The damage was estimated at $8 million with
additional damage to the Burstein Recycling office building which
abuts the building and smoke damage to the Janus Welding Corporation.
A number of Firefighters were treated for smoke inhalation and other
injuries at the scene. Firefighter Edward Bermundez suffered severe
carbon monoxide poisoning and was placed in a hyperbaric chamber at
Massachusetts General Hospital.

Standard Box Fire Timeline

6:10 A.M.

Caller alerts 911 of a fire at Standard Box

6:16 A.M.

Second alarm is sounded – firefighters continue to work inside the building.

6:18 A.M.

Third alarm is sounded

6:41 A.M.

Fourth alarm is sounded – firefighters discover oil is feeding the
fire inside the building.

8:34 A.M.

Fifth alarm is sounded – Building is evacuated and an exterior attack begins.

8:55 A.M.

Sixth alarm is sounded – Building is in danger of collapse –
Equipment is relocated.

9:38 A.M.

Seventh alarm is sounded – Building collapses.

9:41 A.M.

Eighth alarm is sounded for additional help.

3:45 P.M. Sunday

The fire is finally out, two days later.

Debris explodes from Standard Box Company as the
wall of the factory collapses.