The Everett Avenue on-ramp to the Tobin Bridge will be closed overnight on four nights, starting tonight, Wednesday, November 18, the City of Chelsea said in a traffic advisory relaying a Massachusetts Department of Transportation announcement.
The ramp closes at 9 p.m. and reopens at 5 a.m. the next morning. The four nights are:
- Wednesday, November 18, into Thursday morning
- Thursday, November 19, into Friday morning
- Monday, November 30, into Tuesday morning
- Tuesday, December 1, into Wednesday morning
The detour
While the ramp is closed, drivers headed for the bridge southbound toward Boston will be sent to the Arlington Street on-ramp instead, the city said. The advisory tells drivers to expect delays, slow down and use caution in the area.
The closures matter most to people who leave for work before dawn. A driver who normally gets on the bridge at Everett Avenue before 5 a.m. on Thursday, Friday, December 1 or December 2 will find the ramp shut and should allow extra time for the detour.
Why the ramp is closing
The city said the closures give crews room to remove work zone barriers. The state has been repairing and repainting the bridge under a contract the Department of Transportation puts at about $128 million, which it describes as the last of four safety projects to repair steel, strip old paint and repaint the span. The department’s project page says a barrier wall was installed on the Everett Avenue ramp as part of the southbound work, that the old coatings there have been removed and that the new finish coat is in place, with steel repairs continuing through the 2026 season.
Weather could move the dates
All of the work depends on the weather and the schedule could change, the advisory said. Live traffic conditions are posted at mass511.com, and drivers can also dial 511.
The advisory does not say whether more overnight ramp closures will follow after December 1.